Redi-Rock Walls Aid in Innovative Sewer & Storm Water Solution


Large-scale project modernizes and beautifies Cincinnati’s historic Lick Run valley

THE CHALLENGE

During the 19th century, early settlers to Cincinnati, Ohio, followed the Lick Run valley and stream to settle in the developing city along the Ohio River. To control flooding in the area, the stream was enclosed in a 20-foot-diameter storm sewer in 1893. Soon after, during the advent of indoor plumbing, homes were tied into the system to then carry both rainwater and sewage.

After a century of combined use and frequent sewage overflow into nearby Mill Creek during heavy rains, Cincinnati’s Metropolitan Sewer District (MSD) needed a solution for the valley’s worsening pollution crisis.

The massive transformation of the polluted and economically blighted area had to begin with the clearing and retention of the earth in today’s South Fairmont neighborhood between Westwood and Queen City Avenues.

Lick Run Greenway case study before aerial viewProject Groundwork's transformation of the Greenway will extend into future efforts to revitalize the surrounding South Fairmount community.

THE SOLUTION

In accordance with EPA demands to drastically reduce sewage overflow in the valley and throughout the greater Cincinnati area, MSD established a large-scale “green” solution called Project Groundwork in 2009. To address overflow reduction with environmentally, socially, and economically sustainable solutions, a 1.5-mile stretch of the valley would be transformed into both a functional urban waterway and a multi-use community recreational space called Lick Run Greenway.

Eleven Redi-Rock retaining walls were required to support the project’s new infrastructure and to avoid impact to the existing combined sewer, utilities, and roadways. Redi-Rock’s Limestone texture was selected to blend seamlessly with the project’s natural elements.

The construction of the walls was completed in 2020 following the implementation of new storm sewers, stormwater detention basins, and bioswales. The once buried and contained Lick Run stream was resurfaced, in a process called, “daylighting”, as a mile-long constructed waterway through the Greenway. The project’s remaining infrastructure improvements included public recreation areas and gathering spaces, walkways, pedestrian bridges, lighting, and landscaping.

THE DESIGN

Using Redi-Rock Wall+ Software (RRWall+), Justin Amlung, P.E. with Civil Solutions designed the project’s Redi-Rock retaining walls, most of which were needed to retain the earth along Westwood Avenue on Lick Run Greenway’s south border. The remaining Redi-Rock structures served as retaining walls to support grade changes within the greenway.

The gravity walls in the Lick Run project were designed to be constructed with Redi-Rock solid retaining wall blocks. Available in block widths of 28, 41, and 60 in (710, 1030, and 1520 mm), these large wetcast blocks are like one-ton Lego blocks that interlock to build walls up to 15 ft (4.5 m) tall.

Amlung designed a single reinforced retaining wall against an existing roadway abutment using Redi-Rock’s Positive Connection (PC) Blocks for MSE walls. With space to excavate, the use of geogrid wrapped through the PC blocks increased durability and allowed for a taller wall height.

Redi-Rock 9-in (230-mm) step down units were used to address the gradual grade of the roadway abutting many of the Redi-Rock walls. The 9-in blocks, at half the height of standard Redi-Rock blocks, helped ease the transitions at the top of the wall between blocks.

Josh Turton with block supplier Redi-Rock Structures of OKI noted that the step down also allowed the project to meet ODOT dimension requirements for the cast-in-place coping atop the walls.

The retaining walls abutting roadways and waterways were topped with decorative metal guardrails, which added aesthetic appeal and safety measures, and also acted as barriers to restricted waterway areas.

Amlung explained the benefits of utilizing Redi-Rock for the retaining walls within the expansive project.

“[The developer] put a premium on aesthetics and durability,” he said. “When you compare Redi-Rock to a small-block competitor in a water application, there really wasn’t much of a decision to be made.”

Lick Run Greenway case study completedRedi-Rock retaining walls allow multiple options for the incorporation of pedestrian guards or fencing.

THE INSTALLATION

Dave Landwehr, Project Manager with Structures, Inc., Cincinnati who led the installation crew, noted that the project involved numerous challenges like contending with changing traffic patterns along the construction site and tight work spaces between the roadway and new stream bed. The 3-5 man wall construction team utilized an excavator, rubber tire loader, skid steers, and a conveyor belt truck to assist with their work.

The project team constructed a total of 28,000 sq ft (2,601 sq m) of Redi-Rock gravity and reinforced retaining walls to complete this large-scale project spanning 1.5 miles (2.4 kilometers). Although the construction of the walls spanned over two years as the entire project progressed, the total work time occurred in about 30 days, averaging 900 sq ft (83.6 sq m) of walls installed daily.

Lick Run Greenway case study installation of limestone blocksConstruction crews installed 28,000 sq ft (2,601 sq m) of Redi-Rock gravity and reinforced retaining walls in just 30 working days.

THE OUTCOME

At completion in 2021, project planners expect the Lick Run Greenway to cut about 400 million gallons of Combined Sewage Overflows (CSOs) per year. The public walkways and park areas are currently open for the public to enjoy and the native grasses, trees and shrubs added to the valley are expected to be fully established and in full bloom by 2022.

The Lick Run Greenway was named by Storm Water Solutions (SWS) as one of only ten 2022 Top Project honorees across the country. The SWS Top Project awards program "highlights the best storm water and erosion control projects of the year that sought creative solutions." The award recognized the transformation of a long term wastewater problem into a sustainable multi-use solution, dramatically reducing harmful CSOs and providing swaths of usable greenspace in an urban environment.

The success of the Lick Run Greenway project has helped the MSD and the City of Cincinnati more confidently plan future sustainable infrastructure efforts to address environmental issues and continue the community’s economic revitalization.

Lick Run Greenway case studyLick Run stream resurfaces as a part of the Greenway's mile-long constructed waterway.

PROJECT DETAILS

Project Name: Lick Run Greenway #224 Owner: Cincinnati Metropolitan Sewer District Engineer: Justin Amlung, P.E., Civil Solutions Installer: Structures, Inc., Cincinnati Manufacturer: Redi-Rock Structures of OKI Location: Cincinnati, Ohio Year Built: 2020

Aerial imagery provided by the Metropolitan Sewer District of Greater Cincinnati (MSD)


Gravity Retaining Wall Blocks - Massive, one-ton Redi-Rock gravity blocks rely on the sheer mass of each block to hold back the earth.

Reinforced Retaining Wall Blocks - Build MSE retaining walls with the revolutionary Redi-Rock Positive Connection (PC) blocks.

Limestone Texture - Redi-Rock Limestone blocks mimic the texture of natural split Limestone.

Want the newest case studies and tech resources in your inbox?

Sign Up Now